Turn contract dates into a practical payment plan
Small subcontract payment dates can have a big effect on cash flow. This calculator helps you organise an indicative timeline, identify key notice checkpoints, and prepare questions before deadlines become urgent.
See the key dates that may affect when payment is expected and when notices may need attention.
Use one organised timeline instead of relying on scattered notes, emails, or manual date calculations.
Identify the dates and contract points that may need checking with your project team or suitably qualified adviser.
Indicative Payment Timeline
Standard Terms (Unamended)Why contractors use a payment timeline
Payment administration becomes difficult when valuation dates, payment notices, Pay Less Notices, and final payment dates are spread across contract documents and amendments. A structured timeline gives you a practical reference for planning, checking, and discussing the payment process before a deadline is missed.
What you receive
- A structured 12-month payment timeline
- Indicative notice and payment checkpoints
- A clearer reference for cash-flow planning
- Printable PDF output
- Calendar-ready dates
- A practical checklist of points to verify
Generates a commercial planning schedule based on unamended JCT standard rules. Always cross-reference generated dates against your signed contract particulars.
Navigating JCT Subcontract Payment Cycles
Managing cash flow as a trade contractor requires navigating both the underlying statutory provisions of Part II of the Housing Grants, Construction and Regeneration Act 1996 (as amended) and the precise contractual terms in the signed subcontract.
Understanding the Notice Milestones
1. Interim Valuation Date (IVD)
The operational baseline for each assessment cycle, determined by the project programme and the dates specified in the subcontract particulars.
2. Due Date Calculation
The Due Date establishes when payment obligations commence. While standard unamended DBSub provisions stipulate 12 days following the Interim Valuation Date, bespoke main-contractor schedules frequently amend this timeline.
3. Payment Notices vs Default Applications
Under standard JCT mechanisms, the contractor must issue a Payment Notice within 5 days of the Due Date. If the contractor fails to issue a notice and the subcontractor submitted an application in accordance with the contract, that application may constitute the default notice.
4. Pay Less Notice Cut-Offs
To reduce or withhold any payment, an effective Pay Less Notice must be served specifying the basis of deduction. Standard unamended forms stipulate service not later than 5 days prior to the Final Date for Payment, though amended schedules often introduce different prescribed timescales.